A major global biopharmaceutical organization developing a new manufacturing facility in Limerick, Ireland – required a reliable and energy-efficient cooling solution to support a large chiller installation. To support the project requirements, the engineering and project teams partnered with the local Marley Representative Cooling Towers & Accessories (CT&A) to design and deliver a cooling solution capable of supporting phased operational growth and long-term reliability.

The facility required a cooling tower solution that would:
• Support a large-scale chiller installation footprint
• Improve overall energy efficiency
• Simplify and accelerate installation
• Provide operational flexibility during phased production ramp-up

Cooling Tower Case Study - Challenges
Project Challenges

As with many pharmaceutical and biopharmaceutical projects, long-term operational planning was a critical consideration throughout system design. The project team worked closely with the client and engineering stakeholders to develop a cooling solution capable of supporting efficient operation during both startup and future production expansion phases.

Several important criteria were discussed throughout the project, including:
• Supporting phased production growth through an N+1 cooling strategy
• Maintaining efficient operation during periods of reduced cooling demand
• Supporting effective water management and system circulation to reduce conditions associated with biological risk
• Streamlining installation timelines through preassembly and prewiring activities
• Allowing maintenance flexibility while keeping other cells operational

Cooling Tower Case Study - Solutions
Marley Solution

The project team selected Marley® NC Cooling Towers to meet the operational and installation requirements for the facility. The supplied towers included the following specifications:

Tower Models:
Phase 1 – 6 Cells NC8413TCS
Phase 2 – 4 Cells NC8413TCS

Material of Construction: Stainless Steel S304 / Z725 Galvanised Steel
Fill Pack: 15 Mil PVC Fill
Fan Type: Ultra Quiet Fan
Mechanical Configuration: ABB IE4 Electric Motors with Marley Geardrive® and Motor Inside Airstream (MIA) configuration
Special Features:
– Multi-cell FM Factory Mutual Approval
– Sweeper piping
– Control panel recess boxes positioned adjacent to access doors
– VFDs, basin level controls, heater controls and vibration monitoring systems

To improve installation efficiency, the cooling towers were initially delivered to CT&A facilities, where components were prewired and tagged prior to shipment. Fans were installed at a holding location before the towers were delivered to the project site. Six towers were lifted into position within a single week, and overall assembly was completed over a three-week period.

Marley Solution

The project team selected Marley® NC Cooling Towers to meet the operational and installation requirements for the facility. The supplied towers included the following specifications:

Tower Models:
Phase 1 – 6 Cells NC8413TCS
Phase 2 – 4 Cells NC8413TCS

Material of Construction: Stainless Steel S304 / Z725 Galvanised Steel
Fill Pack: 15 Mil PVC Fill
Fan Type: Ultra Quiet Fan
Mechanical Configuration: ABB IE4 Electric Motors with Marley Geardrive® and Motor Inside Airstream (MIA) configuration
Special Features:
– Multi-cell FM Factory Mutual Approval
– Sweeper piping
– Control panel recess boxes positioned adjacent to access doors
– VFDs, basin level controls, heater controls and vibration monitoring systems

To improve installation efficiency, the cooling towers were initially delivered to CT&A facilities, where components were prewired and tagged prior to shipment. Fans were installed at a holding location before the towers were delivered to the project site. Six towers were lifted into position within a single week, and overall assembly was completed over a three-week period.

Cooling Tower Case Study - Solutions
Cooling Tower Case Study - Results
The Results

The Marley NC Cooling Towers successfully satisfied the facility’s cooling load requirements while also providing long-term operational flexibility and installation efficiencies for the project team. Additional project benefits included:

Energy Efficiency: The N+1 cooling solution provides a lower-energy operating approach while also helping reduce noise impact during operation.

Operational Flexibility: The variable-flow capability of the Marley NC allows the facility to gradually increase cooling demand as production expands. The CT&A team liaised with the engineering house to ensure the best approach  to provide effective water circulation during startup and low-load conditions, aligning with water management best practices.

Efficient Installation: Prewiring, tagging and preassembly activities significantly reduced onsite installation complexity and accelerated project timelines.

Advanced Monitoring & Controls: CT&A were appointed to supply and carry out the installation, cabling, termination of the VFDs, vibration monitoring, basin level controls and heater control systems provide operators with enhanced system visibility and improved operational reliability.

The collaboration between the client, engineering house, mechanical contractor, and CT&A/SPX Cooling EMEA helped ensure a successful project outcome. The Marley NC Cooling Towers delivered an energy-efficient and flexible cooling solution designed to support the facility’s phased operational growth while providing the long-term reliability expected from Marley products.

Products and Services Provided

Duty Parameters

  Phase 1 Phase 2
Flowrate (m3/h) 2,381 m3/h  2,084 m3/h
Hot Water Inlet Temperature (°C) 30.9 30.9
Range (°C) 6.9 6.9
Cold Water Outlet Temperature (°C) 24 24
Approach (°C) 5 5
Wet Bulb Temperature (°C) 19 19
Heat Load (kW/h) 18,994 kW (N+1)  16,624 kW
Project Team

Marley Representatives: Cooling Towers & Accessories (CT&A)

Mechanical Contractor(s):  Undisclosed

Project Managers / Engineering:  Undisclosed

Echte Unterstützung durch ein echtes Team

Marley Cooling Towers Logo White

Unsere Kunden sprechen - hören Sie, was sie zu sagen haben:

"Marley war die Marke, von der ich alles über Kühltürme gelernt habe. Bis heute verwenden wir die Cooling Tower Fundamentals als Referenzhandbuch für neue Ingenieure."

"Bei den Produkten von SPX Marley können wir uns immer darauf verlassen, dass die Kühlleistung mit den Daten übereinstimmt, für die sie entwickelt wurde und die versprochen wurden!"
"Wir haben einen Marley-Kühlturm gewartet, seit er 1984 installiert wurde. Es war eine großartige Anlage!


de_DEGerman